All concepts

5. Rates and work

Rates add, times never. Partial work done separately, drains are negative rates.

tank1/6 per hr1/3 per hr1/6 + 1/3 = 1/2 per hr, so 2 hours togetherRates add. Times never add.

Core ideas

- Rates add; times never do. Convert every worker to jobs per hour first.
- Time together = 1 / (sum of rates); for two workers, ab/(a+b) where a and b are their solo times.
- Partial work: multiply rate by time worked to get the fraction done, then ask who finishes the rest.
- A drain is a negative rate: subtract it from the filling rates.

Worked example 1

Machine A makes a batch in 4 hours and machine B in 6 hours. A works alone for 1 hour, then B joins. How long do they work together to finish?

Show solution

Rates: A = 1/4 batch per hour, B = 1/6. In the first hour A completes 1/4, leaving 3/4. Combined rate = 1/4 + 1/6 = 5/12 batch per hour. Remaining time = (3/4) / (5/12) = (3/4) * (12/5) = 9/5 = 1.8 hours, or 1 hour 48 minutes together.

Worked example 2

A pipe fills a tank in 3 hours, a second pipe fills it in 5 hours, and a drain empties a full tank in 6 hours. With all three open, how long to fill the empty tank?

Show solution

Net rate = 1/3 + 1/5 - 1/6. Use 30 as the common denominator: 10/30 + 6/30 - 5/30 = 11/30 tank per hour. Time = 30/11 hours, about 2.73 hours (2 hours 44 minutes). The drain is just a rate with a minus sign; nothing else changes.

Practice set

Question 1

A machine produces 240 units in 8 hours at a constant rate. At this rate, how many units does it produce in 5 hours?






Question 2

Working together at their constant rates, pipes A and B fill a tank in 4 hours. Pipe A alone fills the tank in 6 hours. How many hours does pipe B alone need to fill the tank?






Question 3

Pipe A fills a tank in 3 hours, pipe B fills it in 6 hours, and drain C empties the full tank in 4 hours. If the tank starts empty and A, B, and C are all open, how many hours does it take to fill the tank?






Question 4

Working together at their constant rates, A and B can complete a project in 12 days. They work together for 4 days, then A leaves and B finishes the remaining work alone in 24 days. How many days would A need to complete the entire project alone?